Costs and Benefits of Commissioning
Motivation / Problem Statement
Lack of analysis in this area considered the primary barrier to increased market uptake.
Activities / Approach
Developed and analyzed world's largest database of actual case studies (224 buildings).
Accomplishments / Outcomes
15% median whole-building energy savings; Median payback time 0.7 years; 7000 specific problems identified.
Future / Follow-on
California Energy Commission project to expand database and analysis; Monitoring-based Commissioning — analysis of actual projects throughout the UC/CSU system; Commissioning in high-tech industries
Relationship to Other Projects
Various
Principal Investigator
- Evan Mills
- (510) 486-6784